{"version":"2026-10-02.1","consulted":"2026-10-02","sources":[{"id":"simfer-2026-q2","title":"SimFer — point opérationnel de juin 2026","publisher":"SimFer","url":"https://simfer-sa.com/centre-media/communiques-de-presse/simfer-fait-le-point-sur-lavancement-du-projet-simandou-au-deuxieme-trimestre-2026/","kind":"primary","published":"2026-06-04","reference_year":2026,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Expéditions du T1 2026 et objectif de capacité au S2 2028. Les avancements de mars ne sont pas ceux d’octobre."},{"id":"simfer-port-2026-09","title":"Morébaya — mise en service progressive du terminal SimFer","publisher":"SimFer","url":"https://simfer-sa.com/centre-media/communiques-de-presse/simfer-commence-la-mise-en-service-progressive-dinfrastructures-cles-au-port-de-morebaya/","kind":"primary","published":"2026-09-08","reference_year":2026,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"85 % à fin juin 2026 ; exportations via WCS ; mise en service complète prévue T1 2027."},{"id":"rio-simandou-current","title":"Simandou — opérations et réserves JORC","publisher":"Rio Tinto","url":"https://www.riotinto.com/en/operations/africa/simandou","kind":"primary","published":null,"reference_year":2024,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Note 1 : réserves 2024 publiées le 20/02/2025, réaffirmées sur la page consultée. Blocs 3 et 4 seulement."},{"id":"rio-simandou-2026-q2","title":"Résultats de production du deuxième trimestre 2026","publisher":"Rio Tinto","url":"https://www.riotinto.com/en/news/releases/2026/rio-tinto-releases-second-quarter-2026-production-results","kind":"primary","published":"2026-07-15","reference_year":2026,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Prévision 2026 de ventes SimFer 5–10 Mt, base 100 %, pas un volume réalisé."},{"id":"simandou-programme","title":"Programme national Simandou 2040","publisher":"Direction de cabinet de la Présidence","url":"https://www.simandou2040.gn/","kind":"primary","published":null,"reference_year":2026,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Programme national, cinq piliers et trois vagues ; distinct du projet minier."},{"id":"simandou-wabtec-2026-09","title":"CTG / Wabtec — contrat de services ferroviaires","publisher":"Direction de cabinet de la Présidence","url":"https://www.simandou2040.gn/actualites/ctg-wabtec-contrat-services-ferroviaires-new-york-simandou","kind":"primary","published":"2026-09-21","reference_year":2026,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Engagement de plus de 700 M$ sur plus de dix ans : entretien, formation et contenu local. Ni dépense 2026 ni capacité réalisée."},{"id":"osm-simandou-2026","title":"Quais de Morébaya, camp de Canga et voies du Transguinéen","publisher":"OpenStreetMap contributors","url":"https://www.openstreetmap.org/copyright","kind":"geography","published":null,"reference_year":2026,"consulted":"2026-10-02","license":"ODbL-1.0","verification":"reviewed-geographic-object","note":"Instantanés du 02/10/2026 ; emprises OSM, pas des titres miniers ni un tracé réglementaire. Date de levé inconnue."},{"id":"aga-reserves-2025","title":"Réserves et ressources minérales au 31 décembre 2025","publisher":"AngloGold Ashanti","url":"https://www.anglogoldashanti.com/portfolio/reserves-resources/","kind":"primary","published":null,"reference_year":2025,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Ligne Siguiri (85 %) : tonnage de minerai et or contenu distincts. Ressources déclarées hors réserves."},{"id":"usgs-bauxite-2026","title":"Mineral Commodity Summaries 2026 — Bauxite and Alumina","publisher":"U.S. Geological Survey","url":"https://pubs.usgs.gov/periodicals/mcs2026/mcs2026.pdf","kind":"primary","published":"2026-02","reference_year":2026,"consulted":"2026-10-02","license":"Public domain","verification":"reviewed-primary","note":"Table mondiale : Guinée 7 400 000 milliers de tonnes sèches de réserves de bauxite. Estimation nationale, date de levé inconnue."},{"id":"ins-catalog-check-2026-10-02","title":"Catalogue INS — vérification de la disponibilité des résultats RGPH-4","publisher":"Institut national de la statistique","url":"https://www.stat-guinee.org/index.php/publications-ins/rapports-d-enquetes","kind":"primary","published":null,"reference_year":2026,"consulted":"2026-10-02","license":null,"verification":"reviewed-primary","note":"Consulté le 02/10/2026 : RGPH-4 préliminaire. La rubrique résultats définitifs relève du RGPH-3 (2014)."},{"id":"unesco-fouta-2026","title":"Massif du Fouta Djallon · liste indicative soumise par la Guinée","publisher":"Délégation permanente de la Guinée auprès de l’UNESCO / Centre du patrimoine mondial","url":"https://whc.unesco.org/fr/listesindicatives/7040/","kind":"institutional","license":null,"verification":"published-altitude-reviewed","consulted":"2026-10-02","published":"2026-08-31","reference_year":null,"note":"Soumission à la liste indicative, pas inscription au patrimoine mondial. Hauteur du mont Loura citée ; date de levé et référentiel vertical non précisés."},{"id":"unesco-nimba-height","title":"Paysage culturel des monts Nimba · altitude de Richard-Molard","publisher":"Ministère guinéen de la Culture / Centre du patrimoine mondial UNESCO","url":"https://whc.unesco.org/en/tentativelists/1522/","kind":"institutional","license":null,"verification":"published-altitude-reviewed","consulted":"2026-10-02","published":"2001-03-29","reference_year":null,"note":"Valeur 1 752 m confirmée dans la fiche du bien naturel inscrit https://whc.unesco.org/en/list/155/. Référence géographique historique, pas un levé 2026."},{"id":"rio-simandou-height","title":"Simandou: Khoun na keli · relief dans le périmètre SimFer","publisher":"Rio Tinto / SimFer","url":"https://www.riotinto.com/-/media/content/documents/operations/simandou-khoun-na-keli.pdf?rev=3685ee21e82a45149c438f78ff697353","kind":"operator-publication","license":null,"verification":"published-range-height-reviewed","consulted":"2026-10-02","published":null,"reference_year":null,"note":"Section Building the SimFer mine : partie sud du massif dans la forêt du Pic de Fon, maximum publié 1 650 m. Ce chiffre n’est pas l’altitude certifiée du nœud OSM nommé Simandou."},{"id":"osm-nimba-node","title":"Mont Nimba / Richard-Molard · nœud OSM 321543750","publisher":"Contributeurs OpenStreetMap","url":"https://www.openstreetmap.org/node/321543750","kind":"geographic","license":"ODbL-1.0","verification":"identified-border-summit-node","consulted":"2026-10-02","reference_year":null,"note":"Nœud téléchargé via l’API OSM 0.6, version 10, dernière édition 2023-11-05. Point frontalier Guinée–Côte d’Ivoire ; date de levé inconnue. Altitude publiée jointe depuis l’UNESCO, pas tirée du tag ele."}],"rail_snapshot_sha256":"d0446bdf46ea3f16726ac20a303c79c914f10f86483683f10f2f22bd4cda9258","local_snapshot_sha256":"8a029899e4790406532234f5c04b2de88daeaa3ab883982145f762e8496dd36c","places":[{"id":"canga","name":"SimFer · camp de Canga","map_label":"Canga · SimFer","kind":"mine","scope":"Camp industriel à proximité des opérations des blocs 3 et 4","note":"Centre de l’emprise OSM du camp Rio Tinto, pas un centre de fosse ni un contour de concession. Le tronçon ferroviaire manquant jusqu’à la mine n’est pas inventé.","coordinates":[-8.8808575,8.5577858],"bbox":[-8.8840516,8.5552514,-8.877958,8.5604445],"source_id":"osm-simandou-2026","source_url":"https://www.openstreetmap.org/way/311338477","coordinate_basis":"Centre géométrique de l’objet OSM ; EPSG:4326","survey_date":null},{"id":"massif","name":"Massif du Simandou","map_label":"Massif du Simandou","kind":"mountain","scope":"Sommet cartographié dans la chaîne du Simandou","note":"Repère topographique OSM, pas une limite de concession. Le relief vient du DEM Copernicus ; son millésime d’acquisition reste 2011–2015.","coordinates":[-8.907171,8.5543628],"bbox":[-8.932171,8.5293628,-8.882171,8.5793628],"source_id":"osm-simandou-2026","source_url":"https://www.openstreetmap.org/node/3457472103","coordinate_basis":"Nœud natural=peak OpenStreetMap ; EPSG:4326","survey_date":null,"altitude":{"value":1650,"unit":"m","kind":"range-maximum","scope":"Maximum publié du sud du massif / Pic de Fon · périmètre SimFer","source_id":"rio-simandou-height","source_url":"https://www.riotinto.com/-/media/content/documents/operations/simandou-khoun-na-keli.pdf?rev=3685ee21e82a45149c438f78ff697353","publisher":"Rio Tinto / SimFer","publication_date":null,"consulted":"2026-10-02","survey_date":null,"vertical_datum":null,"license":null,"verification":"published-value-with-explicit-geographic-scope","note":"Le repère OSM situe le massif. 1 650 m décrit le maximum du périmètre présenté par Rio Tinto ; ce n’est pas une mesure de ce point. DEM et maximum publié peuvent différer."}},{"id":"wcs-port","name":"Morébaya · quai WCS","map_label":"Morébaya · WCS","kind":"port","scope":"Quai WCS, rive sud de l’estuaire de Morébaya","note":"Le communiqué SimFer du 8 septembre indique que ses expéditions passent encore par WCS.","coordinates":[-13.3910274,9.4279797],"bbox":[-13.3914809,9.4249111,-13.390574,9.4310484],"source_id":"osm-simandou-2026","source_url":"https://www.openstreetmap.org/way/1415328595","coordinate_basis":"Centre géométrique de l’objet OSM ; EPSG:4326","survey_date":null},{"id":"simfer-port","name":"Morébaya · quai SimFer","map_label":"Morébaya · SimFer","kind":"port","scope":"Quai SimFer, voisin du terminal WCS","note":"Mise en service progressive annoncée le 8 septembre 2026. Mise en service complète prévue T1 2027 ; ce calendrier demeure prévisionnel.","coordinates":[-13.3921497,9.4199361],"bbox":[-13.3926335,9.4164199,-13.391666,9.4234524],"source_id":"osm-simandou-2026","source_url":"https://www.openstreetmap.org/way/1419200844","coordinate_basis":"Centre géométrique de l’objet OSM ; EPSG:4326","survey_date":null}],"metrics":[{"label":"Minerai expédié","value":0.6,"unit":"million de tonnes","scope":"SimFer · premier trimestre 2026","measurement_kind":"shipment","observation":"2026-01-01 / 2026-03-31","publication_year":2026,"source_id":"simfer-2026-q2","locator":"Communiqué du 4 juin · jalons","consulted":"2026-10-02","license":null,"status":"déclaration de l’exploitant","verification":"reviewed-primary","note":""},{"label":"Capacité annuelle visée","value":60,"unit":"millions de tonnes / an","scope":"SimFer · blocs 3 et 4 · cible au second semestre 2028","measurement_kind":"capacity","observation":"Objectif S2 2028 annoncé le 04/06/2026","publication_year":2026,"source_id":"simfer-2026-q2","locator":"Dernier paragraphe · montée en puissance","consulted":"2026-10-02","license":null,"status":"objectif","verification":"reviewed-primary","note":""},{"label":"Capacité commune visée","value":120,"unit":"millions de tonnes / an","scope":"Infrastructure partagée SimFer + WCS, à pleine capacité","measurement_kind":"capacity","observation":"Objectif rappelé le 08/09/2026","publication_year":2026,"source_id":"simfer-port-2026-09","locator":"Dernier paragraphe · capacités portuaires","consulted":"2026-10-02","license":null,"status":"objectif","verification":"reviewed-primary","note":""},{"label":"Avancement du port SimFer","value":85,"unit":"%","scope":"Infrastructures portuaires et maritimes SimFer · fin juin 2026","measurement_kind":"progress","observation":"2026-06-30","publication_year":2026,"source_id":"simfer-port-2026-09","locator":"Communiqué du 8 septembre · avancement","consulted":"2026-10-02","license":null,"status":"déclaration de l’exploitant","verification":"reviewed-primary","note":"Ce taux ne décrit pas l’avancement d’octobre 2026."},{"label":"Réserves de minerai de fer","value":1.5,"unit":"milliard de tonnes","scope":"SimFer · blocs 3 et 4 · base 100 %","measurement_kind":"reserve","observation":"2024-12-31","publication_year":2025,"source_id":"rio-simandou-current","locator":"Note 1 · réserves prouvées + probables JORC","consulted":"2026-10-02","license":null,"status":"estimation publiée","verification":"reviewed-primary","note":"0,2 milliard de tonnes à 66,4 % Fe + 1,3 milliard à 65,0 % Fe ; valeurs arrondies. Ne couvre pas les blocs WCS 1 et 2."}],"rail_note":"Tronçons OSM attribués à la Compagnie du Trans-Guinéen et voies portuaires SimFer. Couverture partielle : aucun trait ne comble un segment absent. Les tags OSM construction peuvent être plus anciens que les communiqués opérationnels. Ce tracé ne certifie ni concession ni disponibilité voyageurs.","length_note":"Les publications n’emploient pas le même périmètre : SimFer annonce un embranchement achevé de 70 km en juin 2026 ; le programme décrit un ensemble ferroviaire de plus de 650 km. Les kilométrages du réseau, de la ligne principale et des embranchements ne sont pas additionnés ici.","guidance":{"lower":5,"upper":10,"unit":"millions de tonnes","scope":"Ventes SimFer prévues pour toute l’année 2026, base 100 %","source_id":"rio-simandou-2026-q2","note":"Prévision publiée le 15 juillet, pas un résultat réalisé ; aucun total 2026 complet disponible au 2 octobre."},"milestones":[{"date":"2026-09-21","title":"Maintenance ferroviaire sur la durée","text":"CTG et Wabtec annoncent un contrat de services de plus de 700 M$ sur plus de dix ans : entretien, formation et contenu local. Il s’agit d’un engagement contractuel.","source_id":"simandou-wabtec-2026-09"},{"date":"2026-09-08","title":"Morébaya : mise en service par étapes","text":"SimFer démarre les équipements de stockage et de chargement. Le minerai continue de partir via WCS ; l’achèvement opérationnel de son propre port reste prévu pour le T1 2027.","source_id":"simfer-port-2026-09"},{"date":"2026-07-15","title":"Une prévision annuelle, pas un total livré","text":"Rio Tinto maintient une prévision de ventes SimFer de 5 à 10 Mt en 2026, sur une base de 100 %. Les premières ventes en Chine ont eu lieu en avril.","source_id":"rio-simandou-2026-q2"},{"date":"2026-06-04","title":"Le rail SimFer entre en exploitation","text":"L’embranchement de 70 km est annoncé achevé et pleinement opérationnel depuis le premier trimestre. SimFer déclare 0,6 Mt expédiée au T1 2026.","source_id":"simfer-2026-q2"}],"programme":{"source_id":"simandou-programme","pillars":["Agriculture, industrie alimentaire et commerce","Éducation et culture","Infrastructures, transports et technologies","Économie, finance et assurances","Santé et bien-être"],"waves":[{"period":"2025–2030","label":"Fondations"},{"period":"2030–2035","label":"Diversification"},{"period":"2035–2040","label":"Consolidation"}],"note":"Le programme national vise une transformation économique plus large que les quatre blocs miniers. Ses annonces ne sont pas assimilées à des réalisations."},"rail_feature_count":467,"rail_geometry_license":"ODbL-1.0","rail_geometry_bytes":154973}